Real-estate investment guidance in Bavaria

054-7513157shamirben@gmail.comBnei Brak · Helmbrechts
Bayern Real EstateBAYERN REAL ESTATE
Contact us

Guides

Buying Off-Plan from a Developer in Germany (Bauträger): Payments, Protections and What to Check

An off-plan apartment in Germany is bought from a developer (Bauträger) who builds the project and sells the apartment together with a share of the land, in a single notarial contract. The law does not let the developer take the money up front. Under the buyer-protection rules, you pay in stages, and only after construction has reached each stage. This is strong protection for the buyer, and alongside it, it pays to check the developer carefully, not just the apartment.

Book an intro call

Updated November 2026 · 12 min read

From our TikTok

Video

This guide in one minute

The key points of this page in a short video. All details, examples and sources are in the text below.

No narration, background music only. The video does not play by itself.

In brief

  • A developer needs a special trade licence and must collect payments by stage: up to 7 payments, each one only after a construction stage has been completed.
  • Before the first payment, several conditions must be met: a valid contract, a priority notice in the land register (Grundbuch), a guaranteed release of prior liens, and a building permit.
  • Instead of stage payments, the developer can provide a full guarantee. In that case earlier payments are allowed.
  • Check the developer the way a bank checks a borrower: accounts, delivered projects, sales and financing.
  • New builds qualify for 5% declining-balance depreciation, and sometimes a special depreciation too, under exact conditions set by law.

What is a Bauträger, and how is it different from a regular contractor?

A Bauträger is a developer who builds on land they own and sells finished units. The contract with them combines two things: a commitment to build, and a commitment to transfer to you ownership of an apartment and a share of the land. The German Civil Code defines this as a developer contract: the rules of a works contract apply to the construction, and the rules of a sale apply to the land transfer. Because land is involved, the contract must be signed before a notary, as in any purchase. More on the notary's role: the notary's role in buying property in Germany.

A regular contractor (Generalunternehmer) builds on land that is already yours. That is the route for someone who bought a plot, and it follows different rules. For an investor buying an apartment in a new building, it is almost always a developer.

The developer needs a trade licence under the German Trade Regulation Act, which explicitly covers anyone who prepares or carries out a building project as owner, in their own name, using buyers' funds. Ask for the licence confirmation and check the company name exactly as it appears in the contract. Often the project is sold by a dedicated subsidiary, not by the better-known developer group.

How do stage payments work?

The regulations set two things. First, threshold conditions: the developer cannot receive any payment until the contract is valid and there is written confirmation from the notary, a priority notice (Vormerkung) has been registered in your favor in the land register, release of the land from earlier liens is secured even if construction is never finished, and a building permit exists. The priority notice is the heart of the protection, and it has its own guide: priority notice (Auflassungsvormerkung).

Second, a table of stages. Up to seven payments may be collected, made up of the following stages:

Construction stage Share
Start of earthworks (when land ownership is transferred) 30% of the contract sum
Shell, including carpentry work on the roof 40% of the balance
Roof covering and gutters 8% of the balance
Heating, plumbing and electrical installations 3% each (9% together)
Windows and glazing 10% of the balance
Interior plaster 6% of the balance
Screed (Estrich) 3% of the balance
Floor tiling and wet-room cladding 4% of the balance
Ready for occupancy, against handover 12% of the balance
Facade 3% of the balance
Full completion 5% of the balance

The "balance" percentages add up to 100% of the 70% that remains after the first payment. If a particular stage does not exist in the project, its share is divided among the others (regulations, version in force 2026).

What is a guarantee instead of stage payments?

The buyer-protection regulations for developers: guarantee instead of stages allow the developer to depart from the stage table if they provide security for the full amount you could claim back. In practice this is usually a bank guarantee or an insurer's guarantee, and it must remain valid until the threshold conditions are met and the building is complete. A developer who asks for a large payment at the start presents such a guarantee. It is the first thing to check.

What about the 5% on completion?

Under the German Civil Code: security for consumers in a construction contract, a consumer who orders construction is entitled to security of 5% of the price for completion on time and without material defects, and if the developer requests it, the consumer holds that amount back from the payments. By law, this rule also applies to a contract with a developer.

Want to check whether this suits you?

Book an intro call

A numerical example: when does the money leave your account?

All the figures here are assumptions for the exercise, not an offer and not a market price.

Assumptions:

  • A new 70 sqm apartment, price 400,000 € (about 5,700 € per sqm).
  • Construction takes 24 months from the start of earthworks.
  • The developer merges the stages into seven payments, as permitted.
  • Financing: 60% from the bank, 40% equity. The bank releases the loan by stages, and a commitment fee (Bereitstellungszins) applies to the part not yet drawn.
Payment Stage Estimated month Amount
1 Earthworks 0 120,000 €
2 Shell 7 112,000 €
3 Roof and installations (heating, plumbing, electrical) 11 47,600 €
4 Windows and interior plaster 15 44,800 €
5 Screed and flooring 18 19,600 €
6 Ready for occupancy, against handover 22 33,600 €
7 Facade and full completion 24 22,400 €
Total 400,000 €

Three things stand out from the table. First: about 58% of the price goes out in the first year, before there is an apartment and before there is rent. Second: in this scenario the first rent arrives in month 23 or 24, and in the meantime you pay interest on the part drawn. So plan your cash flow for those two years in advance. Third: the final 22,400 € is your leverage on defects. Release it only after everything is truly complete.

And what protects you if the developer does not finish the project? The priority notice secures your right to the land and your share of the building, and the release of liens protects you from the developer's bank. In such a case, buyers usually organize together and appoint another contractor to complete the construction. So it pays to keep a cushion for the time and cost of completion, and to choose a developer whose financing is closed.

How do you check the developer before signing?

Check the developer the way a bank checks a borrower. These are the things worth requesting and checking:

  • Financial statements in the official publications register (Bundesanzeiger).
  • Completed and delivered projects, including a visit or a conversation with previous buyers.
  • How many units have already been sold in the project. A project where most units are sold rests on a broad base.
  • Who finances the project, and whether its financing is closed.
  • A guarantee instead of stages, if the developer asks for an early payment.

A project with closed financing and most units sold gives more certainty about the timetable. The general list is in the due diligence checklist.

Depreciation on a new apartment: what the law offers in 2026

This is the big advantage of new construction. Under the German Income Tax Act, for a new residential building whose construction began between 30.9.2023 and 1.10.2029, you can choose declining-balance depreciation of 5% a year of the remaining value, instead of a flat 3%. In the early years this reduces tax considerably more. The full explanation, including the split between land and building: depreciation on German property (AfA).

On top of that there is a special depreciation under the Income Tax Act: special depreciation for new construction: up to an additional 5% a year, in the year of purchase and the three that follow. The conditions are precise: a permit application between 1.1.2023 and 30.9.2029, construction cost up to 5,200 € per sqm, a calculation base of up to 4,000 € per sqm, a building with a high energy-efficiency level (Effizienzhaus 40) with a sustainability certificate, and residential letting for at least ten years. Short-term letting does not count.

An apartment first let after 1.10.2014 is also exempt from the rent brake, as explained under old building or new building (Altbau or Neubau). And if you are weighing a new vacant apartment against an existing one with a tenant: vacant or let.

Financing an off-plan apartment as a non-resident

The bank finances by stages, exactly like the payments to the developer. You pay your equity first, and the bank comes in after it. Beyond the commitment fee, pay attention to three things: the bank needs to see the notarial contract and the stage table before signing, it checks the developer itself, and the fixed-rate period usually starts at signing, not at handover. On the requirements for non-residents: mortgage in Germany for non-residents and bank financing for Israelis. A very energy-efficient building may also open up programs of the state development bank, see KfW loans for investors.

What to check when buying off-plan

  1. The threshold conditions before any payment. The notary's confirmation and a registered priority notice come before the first payment. Every payment follows the notarial contract, never a "deposit to reserve an apartment".
  2. The declaration of division before signing. In a new building, the declaration of division (Teilungserklärung) is written by the developer. Read it and check which rights remain with them. See the declaration of division.
  3. Yield from the day rent begins. Include the two years of construction, with interest, in the yield calculation.
  4. The handover protocol. Record every defect at handover, and confirm "full completion" only after they are fixed.
  5. The project company. Check the company that signs the contract, not just the group's brand.
  6. The conditions for special depreciation. Ask the developer for the documents on energy level and construction cost before including it in your calculation.

Who is an off-plan apartment especially suited for?

An off-plan apartment is especially suited to someone looking for a new, energy-efficient building that is easy to manage, with enhanced depreciation in the early years. It suits an investor with a long horizon, who can plan for two years without rent and examines the developer seriously. Someone who prefers cash flow from the first year will find it in an existing apartment with a tenant. The general comparison between property types and the purchase process appears in the property purchase process in Germany.

Frequently asked questions

What people ask us About the topic

Can a developer in Germany ask for all the money up front?

No, unless they provide a guarantee for the full amount. Without such a guarantee they must collect by stages, up to seven payments, and only after each stage is complete and the threshold conditions are met.

What protects my money if the developer does not finish building?

The priority notice in the land register secures your right to the apartment and your share of the land, and the release of liens protects you from the developer's bank. What needs planning is the time and cost of completing the construction. In such a case buyers usually organize and pay a new contractor for what remains.

What percentage do you pay in the first payment on an off-plan apartment?

Up to 30% of the contract sum, at the start of earthworks, when ownership of the land is transferred. For a leasehold (Erbbaurecht), the share is up to 20%. The other payments are calculated as a percentage of the balance.

Does a new apartment from a developer get enhanced depreciation?

A residential building whose construction began between 30.9.2023 and 1.10.2029 qualifies for declining-balance depreciation of 5% a year. Additional special depreciation requires energy-efficiency conditions, a cost ceiling and ten years of letting. Check with a tax adviser before including it in your calculation.

Is there a rent brake on a new apartment?

Under German tenancy law, the rent brake does not apply to an apartment first used and let after 1.10.2014. What does apply is the cap on increases in an existing contract, so the starting rent is freer, and increases during the lease are limited as usual.

Intro call

We will check the developer before the apartment

Considering an off-plan project? We will go through the contract, the payment table, the guarantees and the calculation of two years without rent with you, in a short call with no commitment.

In the photo: Munich and the Alps, Bavaria

We will not pass your details to anyone else. Prefer WhatsApp? Write to us: 054-7513157